Practice question

When swapping a failed 2070 for a known-good spare on the bench, which step is critical before placing the spare into field service?

  1. Load the agency's controller database/timing file and verify firmware version
  2. Replace the load switches
  3. Reset the CMU clock
  4. Open the BBS battery breaker

Answer: A — Load the agency's controller database/timing file and verify firmware version

The correct answer is shown above. Try the full quiz for additional practice.