Which controller programming step is essential when adding a new EVP approach to an existing 2070?
- Map the preempt input to the desired phase sequence, set entry/dwell/exit timings, and confirm CMU/MMU permissives are compatible
- Replace the load switches
- Increase cycle length to 200 seconds
- Disable the MMU
Answer: A — Map the preempt input to the desired phase sequence, set entry/dwell/exit timings, and confirm CMU/MMU permissives are compatible