Practice question

Which TSP strategy is most likely to be programmed for a bus running 60 seconds late at an arterial coordinated signal?

  1. Green extension and/or red truncation to favor the bus's approach within coordination limits
  2. Force flash for 60 seconds
  3. Drop the local controller to free mode
  4. Disable cross-street phases entirely

Answer: A — Green extension and/or red truncation to favor the bus's approach within coordination limits

The correct answer is shown above. Try the full quiz for additional practice.