Practice question
When returning a rebuilt cabinet to service after a complete bench overhaul, what is the safest final commissioning step before re-energizing the field?
- Perform a complete MMU verification (permissives, red fail, min yellow/clearance, field check, watchdog) and a full controller dry-run with simulated field loads, before connecting field cables
- Connect the field first and observe outputs
- Skip MMU tests if the previous tech signed off
- Disable the BBS during testing
Answer: A — Perform a complete MMU verification (permissives, red fail, min yellow/clearance, field check, watchdog) and a full controller dry-run with simulated field loads, before connecting field cables
The correct answer is shown above. Try the full quiz for additional practice.
Practice more: IMSA Bench Tech II Practice Questions - IMSA Traffic Signal Bench Technician Level II Certification Exam →