Practice question

When returning a rebuilt cabinet to service after a complete bench overhaul, what is the safest final commissioning step before re-energizing the field?

  1. Perform a complete MMU verification (permissives, red fail, min yellow/clearance, field check, watchdog) and a full controller dry-run with simulated field loads, before connecting field cables
  2. Connect the field first and observe outputs
  3. Skip MMU tests if the previous tech signed off
  4. Disable the BBS during testing

Answer: A — Perform a complete MMU verification (permissives, red fail, min yellow/clearance, field check, watchdog) and a full controller dry-run with simulated field loads, before connecting field cables

The correct answer is shown above. Try the full quiz for additional practice.