What is a 'luminaire schedule' in roadway lighting construction documents?

  1. A maintenance calendar for cleaning luminaires
  2. A tabular document listing each luminaire type, manufacturer, model, wattage, distribution type, mounting height, and quantity used in the project
  3. A schedule of when the lights turn on and off
  4. A list of approved lighting contractors

Answer: B — A tabular document listing each luminaire type, manufacturer, model, wattage, distribution type, mounting height, and quantity used in the project

The correct answer is shown above. Try the full quiz for additional practice.