Practice question

What comprehensive documentation package should be provided at project completion for a roadway lighting installation?

  1. Only the invoice
  2. As-built drawings, equipment manuals, warranty information, photometric test results, inspection reports, spare parts list, controller programming documentation, and maintenance procedures
  3. Only the pole manufacturer's brochure
  4. Only the electrical permit

Answer: B — As-built drawings, equipment manuals, warranty information, photometric test results, inspection reports, spare parts list, controller programming documentation, and maintenance procedures

The correct answer is shown above. Try the full quiz for additional practice.

Practice more: IMSA Roadway Lighting II Practice Questions - IMSA Roadway Lighting Technician Level II Certification Exam Exam →