When erecting a traffic signal mast arm pole, what must be verified BEFORE the crane lifts the pole?
- The signal heads are already mounted on the mast arm
- The anchor bolts are properly aligned, plumb, and at the correct projection height
- The controller cabinet is operational
- The detection loops are installed
Answer: B — The anchor bolts are properly aligned, plumb, and at the correct projection height