Practice question
When placing concrete for a drilled shaft foundation, what method is used if groundwater is present in the shaft?
- Bail out all water and pour concrete dry
- Use tremie placement method to place concrete from the bottom up
- Add water to the concrete mix to compensate
- Delay the pour until groundwater recedes
Answer: B — Use tremie placement method to place concrete from the bottom up
The correct answer is shown above. Try the full quiz for additional practice.