What must be inspected and documented BEFORE concrete is placed in a drilled shaft foundation?
- Only the shaft depth
- Shaft depth, diameter, rebar cage placement, anchor bolt template alignment, and groundwater conditions
- Only the rebar cage
- Only the anchor bolt template
Answer: B — Shaft depth, diameter, rebar cage placement, anchor bolt template alignment, and groundwater conditions