As-built drawings must document which of the following for a traffic signal installation?

  1. Only the signal head locations
  2. All deviations from the original construction plans, including actual locations of conduit, poles, pull boxes, and equipment
  3. Only the controller cabinet serial number
  4. Only the cost of materials

Answer: B — All deviations from the original construction plans, including actual locations of conduit, poles, pull boxes, and equipment

The correct answer is shown above. Try the full quiz for additional practice.