Practice question

What is the function of a grout pad between the traffic signal pole base plate and the foundation?

  1. To provide aesthetic appearance
  2. To fill the gap between the base plate and foundation for uniform load distribution
  3. To prevent rust on the anchor bolts
  4. To insulate the pole from electrical current

Answer: B — To fill the gap between the base plate and foundation for uniform load distribution

The correct answer is shown above. Try the full quiz for additional practice.

Practice more: IMSA Signal Construction Practice Questions - IMSA Traffic Signal Construction Technician Level II Certification Exam Exam →