Practice question

What testing must be performed on newly installed conduit before cable is pulled?

  1. No testing is required
  2. A mandrel test to verify the conduit is clear and properly aligned
  3. A pressure test at 50 PSI
  4. A voltage test at 1000V

Answer: B — A mandrel test to verify the conduit is clear and properly aligned

The correct answer is shown above. Try the full quiz for additional practice.