What test verifies that the conflict monitor (MMU/CMU) is functioning properly?
- A visual inspection of the cabinet
- Intentionally programming conflicting phases and verifying the monitor places the signal into flash
- Checking the power supply voltage only
- Measuring the loop detector frequency
Answer: B — Intentionally programming conflicting phases and verifying the monitor places the signal into flash
The correct answer is shown above. Try the full quiz for additional practice.