What test verifies that the conflict monitor (MMU/CMU) is functioning properly?

  1. A visual inspection of the cabinet
  2. Intentionally programming conflicting phases and verifying the monitor places the signal into flash
  3. Checking the power supply voltage only
  4. Measuring the loop detector frequency

Answer: B — Intentionally programming conflicting phases and verifying the monitor places the signal into flash