What is the purpose of the 'shop drawing' review process in traffic signal construction?
- To review the architectural appearance of the signal
- To verify that the contractor's proposed equipment and materials comply with the project specifications before fabrication or procurement
- To sketch the daily work plan
- To design the traffic signal timing
Answer: B — To verify that the contractor's proposed equipment and materials comply with the project specifications before fabrication or procurement