What is the correct procedure for backfilling around a traffic signal foundation?

  1. Dump all backfill material in at once and compact with equipment
  2. Place backfill in lifts of 6-8 inches, compacting each lift to the specified density before placing the next
  3. Use any available soil regardless of type
  4. Backfill is not necessary if the concrete is above grade

Answer: B — Place backfill in lifts of 6-8 inches, compacting each lift to the specified density before placing the next

The correct answer is shown above. Try the full quiz for additional practice.