What is the purpose of a 'pre-construction meeting' for a traffic signal project?

  1. To select the signal timing plan
  2. To establish communication, review plans and specifications, discuss the schedule, and identify potential issues before work begins
  3. To negotiate the contract price
  4. To determine the traffic study results

Answer: B — To establish communication, review plans and specifications, discuss the schedule, and identify potential issues before work begins

The correct answer is shown above. Try the full quiz for additional practice.