What is the proper procedure when the inspector discovers a construction deficiency?

  1. Ignore it if it is minor
  2. Document the deficiency in writing, notify the contractor and the project engineer, and require correction before proceeding
  3. Correct the deficiency personally
  4. Wait until the end of the project to mention it

Answer: B — Document the deficiency in writing, notify the contractor and the project engineer, and require correction before proceeding

The correct answer is shown above. Try the full quiz for additional practice.