What is the purpose of the 'final acceptance test' for a traffic signal installation?

  1. To test the contractor's knowledge of signal operation
  2. To verify that all components are installed correctly, functioning properly, and the complete system operates as designed before the agency accepts the project
  3. To determine the signal timing plan
  4. To test the warranty coverage

Answer: B — To verify that all components are installed correctly, functioning properly, and the complete system operates as designed before the agency accepts the project