Practice question
What is the correct procedure when the contractor proposes using a material that differs from the project specifications?
- Accept any substitution the contractor proposes
- Require the contractor to submit a formal substitution request with documentation showing the proposed material meets or exceeds specifications, for the engineer's review and approval
- Reject all substitutions without review
- Allow substitutions only for less expensive materials
Answer: B — Require the contractor to submit a formal substitution request with documentation showing the proposed material meets or exceeds specifications, for the engineer's review and approval
The correct answer is shown above. Try the full quiz for additional practice.
Practice more: IMSA Signal Inspector Practice Questions - IMSA Traffic Signal Inspector Certification Exam Exam →