Practice question
What is the difference between a 'change order' and a 'field order' in traffic signal construction?
- They are the same thing
- A change order formally modifies the contract (scope, cost, time) and requires written approval; a field order is a minor directive that does not change the contract value or scope
- A field order is more formal than a change order
- Change orders are verbal; field orders are written
Answer: B — A change order formally modifies the contract (scope, cost, time) and requires written approval; a field order is a minor directive that does not change the contract value or scope