What is the inspector's role when the contractor encounters unforeseen underground conditions (rock, contaminated soil, unknown utilities)?
- Ignore the condition and continue
- Document the condition immediately, stop work in the affected area, notify the project engineer, and await direction before the contractor proceeds
- Tell the contractor to figure it out on their own
- Authorize additional payment immediately
Answer: B — Document the condition immediately, stop work in the affected area, notify the project engineer, and await direction before the contractor proceeds
The correct answer is shown above. Try the full quiz for additional practice.