Practice question
What is the purpose of 'force-off' in a coordinated signal timing plan?
- To manually override the controller and turn off all signals
- To terminate a non-coordinated phase at its maximum time to allow the coordinated phase to begin at the correct time
- To force pedestrian clearance intervals to end early
- To disable emergency vehicle preemption during coordination
Answer: B — To terminate a non-coordinated phase at its maximum time to allow the coordinated phase to begin at the correct time
The correct answer is shown above. Try the full quiz for additional practice.