Practice question
When programming railroad preemption, what is the 'advance preemption time'?
- The time from when the controller receives the preemption call to when it begins the preemption sequence
- The time provided by the railroad warning system before the gates descend, allowing the signal to clear traffic from the tracks
- The time added to the walk interval for pedestrians near the railroad crossing
- The time the signal remains in flash after the train passes
Answer: B — The time provided by the railroad warning system before the gates descend, allowing the signal to clear traffic from the tracks