Practice question

What is the primary goal of Temporary Traffic Control (TTC) in a work zone?

  1. To speed up construction work
  2. To provide for the reasonably safe and efficient movement of road users through or around work zones while protecting workers
  3. To eliminate all traffic from the work area
  4. To generate revenue from traffic fines

Answer: B — To provide for the reasonably safe and efficient movement of road users through or around work zones while protecting workers

The correct answer is shown above. Try the full quiz for additional practice.

Practice more: IMSA Work Zone Practice Questions - IMSA Work Zone Temporary Traffic Control Technician Certification Exam Exam →