What is the proper order for setting up a TTC zone?

  1. Start closest to the work area and work outward
  2. Start with the most upstream advance warning signs and work downstream toward the work area
  3. Start with the termination area and work backward
  4. Set up all signs simultaneously

Answer: B — Start with the most upstream advance warning signs and work downstream toward the work area