When is a pile splice typically required on a highway bridge foundation?
- Whenever the pile is timber, because timber cannot be driven in one piece
- When the required embedded length exceeds what can be shipped, handled, or pitched in one piece
- On every pile, because splices increase capacity above a one-piece pile
- Only above the finished cutoff elevation so the splice stays visible
Answer: B — When the required embedded length exceeds what can be shipped, handled, or pitched in one piece
The correct answer is shown above. Try the full quiz for additional practice.