Why must newly placed concrete pavement be cured?
- To keep enough moisture and a favorable temperature in the slab so hydration can continue and plastic-shrinkage cracking is reduced
- To stain the surface so inspectors can see the pour
- To eliminate the need for any joints
- To lower the 28-day strength on purpose
Answer: A — To keep enough moisture and a favorable temperature in the slab so hydration can continue and plastic-shrinkage cracking is reduced