A crane will operate near an overhead power line and the voltage is not yet known. Under OSHA 1926.1408, which approach is acceptable?
- Assume any clearance is fine if the operator has 10 years of experience
- De-energize and ground the line, or keep the equipment, load line, and load at least 20 feet away until voltage is identified and Table A or another permitted option is used
- Use a 3-foot clearance because boom trucks are exempt
- Touch the line briefly with a tag line to test whether it is energized
Answer: B — De-energize and ground the line, or keep the equipment, load line, and load at least 20 feet away until voltage is identified and Table A or another permitted option is used
The correct answer is shown above. Try the full quiz for additional practice.