Practice question
Except for emergency or other statutory exceptions, how much advance notice must a Mississippi excavator give MS 811 before beginning excavation?
- Not less than 3 and not more than 10 working days
- At least 30 calendar days and not more than 90 calendar days
- Notice is optional if the contractor has a highway permit
- Notice is required only after a utility is damaged
Answer: A — Not less than 3 and not more than 10 working days
The correct answer is shown above. Try the full quiz for additional practice.
Practice more: MS Highway Practice Questions - Mississippi Highway Contractor Examination Exam →