In MUTCD temporary traffic control, what is the usual sequence of a work-zone layout along the road?

  1. Termination area, then activity area, then advance warning
  2. Advance warning area, transition area, activity area (buffer space plus work space), then termination area
  3. Only an activity area; warning signs are optional on high-speed roads
  4. Buffer space only, with no signs or tapers

Answer: B — Advance warning area, transition area, activity area (buffer space plus work space), then termination area