Practice question
What is the primary purpose of placing timber mats or crane mats under the tracks of a dedicated pile driving rig?
- To increase the operating speed of the tracks
- To distribute the machine's weight and reduce ground bearing pressure on the supporting surface
- To electrically insulate the rig from the ground
- To eliminate the need to check the load chart
Answer: B — To distribute the machine's weight and reduce ground bearing pressure on the supporting surface
The correct answer is shown above. Try the full quiz for additional practice.
Practice more: NCCCO Dedicated Pile Driver Practice Questions - NCCCO Dedicated Pile Driver Operator (DPD) Exam →