Practice question
When selecting rigging to hoist a pile into the leads, which factor must the operator verify FIRST?
- That the sling/rigging working load limit (WLL) exceeds the pile weight including any sling angle effects
- That the sling matches the paint color of the rig
- That the rigging is the longest available regardless of capacity
- That the rigging has never been inspected
Answer: A — That the sling/rigging working load limit (WLL) exceeds the pile weight including any sling angle effects
The correct answer is shown above. Try the full quiz for additional practice.
Practice more: NCCCO Dedicated Pile Driver Practice Questions - NCCCO Dedicated Pile Driver Operator (DPD) Exam →