Practice question

When selecting rigging to hoist a pile into the leads, which factor must the operator verify FIRST?

  1. That the sling/rigging working load limit (WLL) exceeds the pile weight including any sling angle effects
  2. That the sling matches the paint color of the rig
  3. That the rigging is the longest available regardless of capacity
  4. That the rigging has never been inspected

Answer: A — That the sling/rigging working load limit (WLL) exceeds the pile weight including any sling angle effects

The correct answer is shown above. Try the full quiz for additional practice.

Practice more: NCCCO Dedicated Pile Driver Practice Questions - NCCCO Dedicated Pile Driver Operator (DPD) Exam →