Practice question

What is 'refusal' in pile driving?

  1. When the operator refuses to drive a pile
  2. The point at which the pile advances little or no further per blow (or per specified blow count), indicating the pile has met required resistance/depth
  3. When the hammer runs out of fuel
  4. When the crane refuses to start

Answer: B — The point at which the pile advances little or no further per blow (or per specified blow count), indicating the pile has met required resistance/depth

The correct answer is shown above. Try the full quiz for additional practice.

Practice more: NCCCO Dedicated Pile Driver Practice Questions - NCCCO Dedicated Pile Driver Operator (DPD) Exam →