Practice question

Why must the operator not exceed the manufacturer's stated limitations for the hammer (such as maximum energy or stroke) for a given pile?

  1. Exceeding limits voids only the paint warranty
  2. Over-driving can crack or damage the pile, overstress the leads and rig, and create unsafe dynamic loads
  3. Higher energy always installs piles faster with no downside
  4. Manufacturer limits apply only to the practical exam

Answer: B — Over-driving can crack or damage the pile, overstress the leads and rig, and create unsafe dynamic loads