Predrilling (or 'spudding') may be used before driving a pile primarily to:

  1. Increase the pile's weight
  2. Penetrate hard upper layers or obstructions and guide the pile, reducing the risk of damage and refusal in the upper soils
  3. Paint the pile underground
  4. Eliminate the need for a hammer

Answer: B — Penetrate hard upper layers or obstructions and guide the pile, reducing the risk of damage and refusal in the upper soils

The correct answer is shown above. Try the full quiz for additional practice.