Practice question

Which rigging hardware is appropriate for connecting a sling to a lifting point on a pile, provided it is rated for the load?

  1. A shackle with a properly seated pin
  2. A bent piece of rebar
  3. A length of chain-link fence wire
  4. An unrated piece of scrap pipe

Answer: A — A shackle with a properly seated pin

The correct answer is shown above. Try the full quiz for additional practice.

Practice more: NCCCO Dedicated Pile Driver Practice Questions - NCCCO Dedicated Pile Driver Operator (DPD) Exam →