Before initiating the driving sequence, the leads holding the hammer and pile should be:

  1. Leaning at least 10 degrees off vertical
  2. Plumb (within close tolerance) so driving energy is delivered concentrically along the pile axis
  3. Resting against the tracks
  4. Disconnected from the rig

Answer: B — Plumb (within close tolerance) so driving energy is delivered concentrically along the pile axis