Practice question

Which of the following is the correct sequence concept when finishing work with a dedicated pile driving rig?

  1. Transport first, then stow the hammer and lower the leads
  2. Stow/secure the hammer and lower/retract the leads, then secure components, then transport within legal limits
  3. Leave everything in the driving position and drive home
  4. Remove the counterweight before lowering the leads

Answer: B — Stow/secure the hammer and lower/retract the leads, then secure components, then transport within legal limits

The correct answer is shown above. Try the full quiz for additional practice.

Practice more: NCCCO Dedicated Pile Driver Practice Questions - NCCCO Dedicated Pile Driver Operator (DPD) Exam →