Practice question

Which factor most directly limits the maximum sustainable fill rate at a static source draft fill site?

  1. Length of the tanker dump hose
  2. Pumper's drafting capability and supply hose layout
  3. Air temperature
  4. Number of crew members at the fill site

Answer: B — Pumper's drafting capability and supply hose layout

The correct answer is shown above. Try the full quiz for additional practice.

Practice more: NFPA D O Mobile Water Supply Practice Questions - NFPA 1002 Driver/Operator - Mobile Water Supply Apparatus Exam →