When a specification section and a plan note appear to conflict, what should the inspector do first?

  1. Direct the contractor based on memory
  2. Use whichever requirement is cheaper
  3. Document the conflict and request clarification through the proper chain
  4. Ignore the note and continue work

Answer: C — Document the conflict and request clarification through the proper chain

The correct answer is shown above. Try the full quiz for additional practice.