When a specification section and a plan note appear to conflict, what should the inspector do first?
- Direct the contractor based on memory
- Use whichever requirement is cheaper
- Document the conflict and request clarification through the proper chain
- Ignore the note and continue work
Answer: C — Document the conflict and request clarification through the proper chain