If the existing ground elevation is 98.4 feet and the proposed subgrade is 97.9 feet, what operation is needed at that point?

  1. Fill 0.5 foot
  2. Cut 0.5 foot
  3. Fill 1.0 foot
  4. No change is needed

Answer: B — Cut 0.5 foot