Practice question
Locator marks show a utility crossing the proposed trench line. What should occur before machine excavation directly at the crossing?
- Increase excavator speed so exposure happens quickly
- Pothole or otherwise carefully expose the utility to verify its location
- Remove the locator marks so they do not confuse the crew
- Wait until the end of the day to investigate
Answer: B — Pothole or otherwise carefully expose the utility to verify its location
The correct answer is shown above. Try the full quiz for additional practice.