Practice question

Locator marks show a utility crossing the proposed trench line. What should occur before machine excavation directly at the crossing?

  1. Increase excavator speed so exposure happens quickly
  2. Pothole or otherwise carefully expose the utility to verify its location
  3. Remove the locator marks so they do not confuse the crew
  4. Wait until the end of the day to investigate

Answer: B — Pothole or otherwise carefully expose the utility to verify its location

The correct answer is shown above. Try the full quiz for additional practice.