Practice question

Before hot-mix asphalt placement begins, which document should the inspector verify matches the mix being delivered?

  1. The approved job mix formula
  2. The payroll roster
  3. The stormwater pollution prevention plan
  4. The project baseline schedule

Answer: A — The approved job mix formula

The correct answer is shown above. Try the full quiz for additional practice.