Practice question

If an asphalt plant changes aggregate source or binder grade, what is typically needed before the mix can continue to be accepted?

  1. Nothing, if the temperature stays the same
  2. A revised and approved job mix formula
  3. Extra flaggers only
  4. A new lane-closure permit only

Answer: B — A revised and approved job mix formula

The correct answer is shown above. Try the full quiz for additional practice.