An issued plan revision changes a storm drain from 18 in to 24 in RCP, but the contractor's older printed sheet still shows 18 in. What governs the inspection?

  1. The oldest plan set on site
  2. The contractor's takeoff worksheet
  3. The latest issued revision in the contract documents
  4. The pipe size that is already in the supplier's yard

Answer: C — The latest issued revision in the contract documents