An issued plan revision changes a storm drain from 18 in to 24 in RCP, but the contractor's older printed sheet still shows 18 in. What governs the inspection?
Answer: C — The latest issued revision in the contract documents
The correct answer is shown above. Try the full quiz for additional practice.