Practice question

When a project-specific requirement conflicts with a general standard specification, which document usually provides the project-specific governing requirement?

  1. The contractor's quality control manual
  2. The manufacturer's catalog cut sheet
  3. The special provisions or supplemental specifications
  4. A standard detail from an unrelated project

Answer: C — The special provisions or supplemental specifications

The correct answer is shown above. Try the full quiz for additional practice.

Practice more: NICET HCI Practice Questions - NICET Highway Construction Inspection Exam →