Practice question

During proof rolling, the subgrade pumps and rutting develops under the roller. What does this most likely indicate?

  1. The material is too wet or unstable and needs correction before paving
  2. The subgrade is ready for base course immediately
  3. The roller is too heavy, but the soil condition is acceptable
  4. The surface only needs to be bladed smooth

Answer: A — The material is too wet or unstable and needs correction before paving

The correct answer is shown above. Try the full quiz for additional practice.

Practice more: NICET HCI Practice Questions - NICET Highway Construction Inspection Exam →