Practice question
During proof rolling, the subgrade pumps and rutting develops under the roller. What does this most likely indicate?
- The material is too wet or unstable and needs correction before paving
- The subgrade is ready for base course immediately
- The roller is too heavy, but the soil condition is acceptable
- The surface only needs to be bladed smooth
Answer: A — The material is too wet or unstable and needs correction before paving
The correct answer is shown above. Try the full quiz for additional practice.
Practice more: NICET HCI Practice Questions - NICET Highway Construction Inspection Exam →