Before a trench crosses a marked gas main, which field method best verifies the utility's exact location and depth?

  1. Reviewing record drawings only
  2. Vacuum potholing or daylighting
  3. Estimating from paint marks on the pavement
  4. Using the nearest valve box as the crossing control point

Answer: B — Vacuum potholing or daylighting