Before a concrete pavement pour begins, what is one of the most important things to verify about dowel baskets or dowel assemblies?

  1. They are aligned and secured so they will not move during paving
  2. They are painted the same color as the pavement forms
  3. They are placed as close to the subgrade as possible
  4. They are removed as soon as the first concrete is discharged

Answer: A — They are aligned and secured so they will not move during paving

The correct answer is shown above. Try the full quiz for additional practice.