Density at a longitudinal asphalt joint is consistently low because the cold side has a vertical unsupported edge and little confinement. Which field adjustment is most likely to help?
- Lower the paver speed only and make no other changes
- Improve joint construction and rolling so the hot side is properly overlapped and confined
- Reduce the number of rollers so the mat cools faster
- Skip density checks at the joint because they are always lower
Answer: B — Improve joint construction and rolling so the hot side is properly overlapped and confined
The correct answer is shown above. Try the full quiz for additional practice.